Tuesday, March 30, 2010
Retrofit update
We’re about 70% done with the retrofit and plan it to be completed by the end of April. We have excavated part of the floor on the first level, have installed rebar and we're pouring the concrete underneath the wood floors today. (You'll note in the photo, this is the bar to the left as you walk in the front door, We are pouring the concrete underneath the whole floor.) Next step, insert large steel I-Beams which will stabilize the walls and floors and the roof. This is exciting.